This page contains all baselined requirements documentation, along with outstanding change requests.
The document can be broken down into three types of requirements.
- Trading & Settlement Code Documentation: Includes the latest version of the Code and the Agreed Procedures. Changes to these documents must go through the Joint Change Control Panel.
- Regulatory Requirements Document: This document contains further elaboration on the Trading & Settlement Code and Agreed Procedures, and reflects decisions from the Regulatory Authorities and from other SEM Workstreams interacting and arising in parallel with the SEM design. A piece of work is in train to map this document to Code requirements and decision documentation of Ofreg and CER. Changes to this document are impact assessed at the SIMDRACS Board.
- SEM Implementation Team documentation: This documentation is SEMIT’s technical specification of the interface with the Metered Data Providers. The Metered Data Providers use a different interface to the Market Participants. These documents are under control of SEMIT and changes are delivered to the SIMDRACS Board as they arise.
Documentation Release History
Release #1. 21st of September 2006
Release #2: 5th of October 2006
- T&SC change requests linked off-site
- Added change control request template
- New change request SIMDRACS_1.doc added with regard to Baselined v1.0 Regulatory Requirements document: affecting W-RMO-ALL-23.1
- New change request SIMDRACS_2.doc added with regard to Baselined v1.0 Regulatory Requirements document: affecting SONI and NIE T&D Appendix
- New Metered Data Providers communication interface with the central market systems, to replace the Baselined v1.0 API Specification
- New testing documentation which gives high-level information about integration testing
Release #3: 11th of October 2006
- Split table into sections, indicating
- Baselined documents, with references to the change requests and action items which are related to them, and where the document has been baselined
- Pre-baselined documents, naming the meeting at which they are to be baselined
- Change requests and their status
- Documents under development - Updated Regulatory Requirements document to Version 1.1 following acceptance of SIMDRACS_2
Release #4: 12th of October 2006
- Added clarifications to SIMDRACS_1 change request, updating it to SIMDRACS_1a
Release #5: 16th of October 2006
- Updated Baselined Document #6 Metered Data File Format Version 1.2 to Version 1.3. Version 1.3 was baselined at the SIMDRACS Meeting on the 14th of September, and therefore has no change request is associated with the update which does not materially differ technically from Version 1.2
- Added change control SIMDRACS_5, in relation to the Baselined Document #6: TIME_CREATED field altered to a per second precision
Release #6: 02nd of November 2006
- SIMDRACS_3 related to making the time-stamp in the metered data format a required field accepted
- SIMDRACS_5 related to making the time-stamp to a second precision accepted
- SIMDRACS_4 accepted, its description corrected to changes to the API document
- Information for Document #6 Metered Data File Format Version 1.2 updated to reflect SIMDRACS_3 and SIMDRACS_5. Note that this document will be updated to Version 1.4 to reflect these changes at a later time.
- Information and documentation for Document #4: API Specification, updated to Version 1.1 arising from SIMDRACS_4. Deleted the appropriate pre-baseline document from the pre-baseline section. Comments are added to this section, indicating that this document is subject to a different form of change control - i.e. changes to this document must be accepted, and consequently any impact to the Metered Data Providers in terms of cost, timelines, and quality (subject to a reasonableness review) will be accepted.
- Added SIMDRACS_1b to update SIMDRACS_1a, which is in relation to W-RMO-ALL-32 in Document #2: Regulatory Requirements Document. SIMDRACS_1b reflects recent discussions with NIE T&D and ESB Networks.
Release #7: 08th of November 2006
Release #8: 5th of December 2006
- SEMIT Agreed Procedures Version 2.0 added to the baselined documentation
- Username to access AIME site: CERegulation
- Password to access AIME site: t7ethlu6 - RA Agreed Procedures Version 2.0 added to the baselined documentation
- Detail of the Market Trial added to the baselined documentation
- A clarification note around Trading Sites added to the baselined documentation
- The proposed Alternative to RA324 has been added to the baselined documentation. This primarily affects the Ireland MDPs at this time.
- Appendix 3 to Agreed Procedure 1 is now baselined as part of Agreed Procedure 1
- SIMDRACS_1b is now baselined and incorporated into updated Regulatory Requirements Document version 1.2 on the basis that is now being implemented by the RMOs
- Developing documentation now contains two documents that have been circulated to industry but have not been through the formal change control process. These are the legal review of the T&SC Version 1.1, and an updated Version 3.0 of Agreed Procedure 1.
- Actions related to the various documents have been updated. Also see the updated Action List in the Reporting section.
Release #9: 8th of January 2007
- * The following SIMDRACS change controls have been raised:
- SIMDRACS_6 against Regulatory Requirements (ver 1.2): Out-of-market trading - historical Supplier Unit volumes need only be 1.5 times maximum contracted generation
- SIMDRACS_7 against Regulatory Requirements (ver 1.2): Out-of-market trading - information to send to suppliers when Supplier Unit volumes set to zero
- SIMDRACS_8 against SEM-MDP Meter Data Format (ver 1.4): Allowed values of Actual/Estimated Flag in the file format
- SIMDRACS_9 against Regulatory Requirements (ver 1.2): Rules for counting actual reads for "MPRNs" aggregation for out-of-market generation in Ireland
- SIMDRACS_10 against Regulatory Requirements (ver 1.2): Rules for counting actual reads when two 15-minute readings are aggregated into a half-hourly volume
- RAyyy (yyy number to be confirmed) against the T&SC Version 1.0: Baselining Agreed Procedure 16
- RAzzz (zzz number to be confirmed) against the T&SC Version 1.0: Rewording rejected RA347 - The following SIMDRACS change controls have been rejected:
- RA333 - due to difficulties in the timelines for the publication of data - replaced with RAyyy
- RA347 - due to wording difficulties - replaced with RAzzz
- RA334 - due to difficulties in the creation of an extra invoice - a replacement for RA334 will follow as soon as it has been work-shopped with the SEMIT
Release #10: 10th of January 2007
- The following SIMDRACS change control has been raised:
- RAxxx (xxx number to be confirmed) against the T&SC Version 1.0, and Agreed Procedure 13 Version 1.0. (It also cleans up some related text in Agreed Procedure 15 - Agreed Procedure 15 otherwise has not been identified as having an impact on Metered Data Providers).
Release #11: 12th of January 2007
The following SIMDRACS change control has been raised:
- SIMDRACS_11 changing the xml and wsdl of the API interface to remove embedded date from all VALUE fields. This change replaces baselined Document 4 - the API of the Navita Interface. This affects all Metered Data Providers
Release #12: 26th of January 2007
The updates to SIMDRACS change control are posted:
- SIMDRACS_6, SIMDRACS_7, and SIMDRACS_8 were accepted. Regulatory Requirements Document updated to Version 1.3. SEM-MDP Metered Data File Format updated to Version 1.5
- SIMDRACS_13 is raised and seeks to align Version 0.2 of the Meter Data Format Data Definitions to align with Version 1.5 of the SEM-MDP Metered Data File Format. This includes the effects of SIMDRACS_3, SIMDRACS_5, and SIMDRACS_8 on the Meter Data Format Data Definitions
- SIMDRACS_12 is raised and sets out the requirement that the data query flag is always set to zero. This relies on RA412 (formally RAxxx) being accepted by the JCCP. This affects both the Meter Data Format Data Definitions and SEM-MDP Metered Data File Format
- RA-Legal has been raised, containing changes embedded in the legal review of the Code
- RAvvv setting out that Metered Data Providers must send in data to the SMO in the event of a failure within 2 Working Days for either technical or communication reasons. This change against the Trading & Settlement Code
- An altered RA322 which was rejected, containing a language change to require Generator Units to have interval metering, including some new provisions
- A cut-down RAyyy which seeks to bring Agreed Procedure 16 under the Code
- RAzzz which sets out the requirements for SCADA for Generator Units that are not Autonomous - RAxxx has been sent to the JCCP for processing and is now called RA412
- RAwww (first incomplete draft) is raised and sets out the processes for what data set out in Appendix 3 of AP1 flows when during Registration events. This change request is against Agreed Procedure 1
- SIMDRACS_9, SIMDRACS_10 status updated to "Once EirGrid confirms, this is baselined"
- SIMDRACS_11 status updated to "Decision to baselined deferred until response to Query 19 with SEMIT"
Release #13: 31st of January 2007
The updates to SIMDRACS change control are posted:
- RAwww (first complete draft) is raised and sets out the processes for what data set out in Appendix 3 of AP1 flows when during Registration events. This change request is against Agreed Procedure 1
Release #14: 8th of February 2007
The updates to SIMDRACS change control are posted:
Baselined Documents
Document 1
This document is under the SIMDRACS Board Change Control Process. The following SIMDRACS Actions and Change Controls pertain to this document.
|
| Name | Date | Ver. | Comments | Link |
|---|
| RA323 | 10/08/2006 | | This change control allows Supplier Units to go negative. relates to document #3 - the T&SC v1.0. A consequence of this change control is that it will impact RA324. This change request is currently being drafted to circulate to the SIMDRACS Board. | Onsite |
| RA324 | 10/08/2006 | | This change control relates to Baselined Doc #3: T&SC v1.0. A consequence of this change control is that it will impact RA324. This change request is currently being drafted to circulate to the SIMDRACS Board. | Onsite |
| RA333 | 19/09/2006 | | This T&SC Change control will bring this document underneath the T&SC Change Control Process | Onsite |
| RAyyy | 19/12/2006 | | This T&SC Change Control replaces the rejected RA333; this change control also seeks to place AP16 under the change control process | Onsite |
| RA-Legal | 26/01/2007 | | Version 0.1 Contains an amalgamation of RAyyy, RAzzz, RA322 and RAvvv | Onsite |
Document 2
This document is under the SIMDRACS Board Change Control Process. The following SIMDRACS Actions and Change Controls pertain to this document
|
| Name | Date | Ver. | Comments | Link |
|---|
| RA324 | 19/09/2006 | | This change request pertains to the responsibilities of EirGrid and ESB Networks as set out in Appendix B. | Offsite |
| TSO_RA_CR2 | 13/09/2006 | | This change request pertains to the responsibilities of EirGrid and ESB Networks as set out in Appendix B. | Onsite |
| Actions 65,66 | | | Relate to Appendix B and TSO_RA_CR2: 65 and 66 relate to the scope of TSO_RA_CR2 | Offsite |
| Action 181 | | | Relates to the meaning of Estimated and Actual where EirGrid pass data to ESB Networks | Offsite |
Document 3
| Name | Date | Ver. | Comments | Link |
|---|
| T&SC | 15/02/2006 | 1.0 | Of interest for legal requirements and the high-level source for all other detailed requirements | Onsite |
This document is under the T&SC Change Control Process. The following SIMDRACS Actions and Change Controls pertain to this document
|
| Name | Date | Ver. | Comments | Link |
|---|
| RA322 | | | New interval metering requirement for Trading Sites | Onsite |
| RA323 | | | Supplier Units should be allowed to go negative | Onsite |
| RA324 | | | Changes to the firm/non-firm access calculation | Onsite |
| RA333 | | | To bring AP16 into the Code | Onsite |
| RA334 | | | To change the Data Query Process | Onsite |
| RA347 | | | New SCADA requirement for non-autonomous Generator Units | Onsite |
| RA412 | 10/01/2007 | | Removes the requirements for setting the Data Query Flag | Onsite |
| RAyyy | 08/01/2007 | | Replaces RA333: To bring AP16 into the Code | Onsite |
| RAzzz | 08/01/2007 | | Replaces RA347: A rewording change | Onsite |
| RA-Legal | 26/01/2007 | | Version 0.1 Contains an amalgamation of RAyyy, RAzzz, RA322 and RAvvv | Onsite |
Document 4
|
| Name | Date | Ver. | Comments | Link |
|---|
| API Specification | 24/10/2006 | 1.1 | Version 1.1 is a completely new API, which was brought through the SIMDRACS_4 change control. | Onsite |
| API Specification | 06/09/2006 | 1.0 | Refer to the content of the cover note in MS Outlook message | Onsite |
This document can be changed by the builders of the central market system and moved into implementation without impact analysis from the SIMDRACS Board. Consequently, the impacts on Metered Data Providers of any such changes in terms of cost, timelines, or quality (subject to a reasonableness review) will be accepted as unavoidable.
The following change control pertains to this document
| Name | Date | Ver. | Comments | Link |
|---|
| SIMDRACS_11 | 12/01/2007 | | Changes the xml and wsdl of the API interface to remove embedded date from all VALUE fields | Onsite |
Document 5
This document is under the SIMDRACS Board Change Control Process. The following change controls pertain to this document.
|
| Name | Date | Ver. | Comments | Link |
|---|
| SIMDRACS_12 | 25/01/2007 | | To set the Data Query Flag to zero as it is not being used: relies on RAxxx being accepted | Onsite |
| SIMDRACS_13 | 25/01/2007 | | To align Metered Data Format Data Definitions with the SEM-MDP Metered Data File Format | Onsite |
Document 6
This document is under the SIMDRACS Board Change Control Process. The following change control relates to this document
|
| Name | Date | Ver. | Comments | Link |
|---|
| SIMDRACS_12 | 25/01/2007 | | To set the Data Query Flag to zero as it is not being used: relies on RAxxx being accepted | Onsite |
| SIMDRACS_8 | | | | Onsite |
Document 7
This document is provided for information purposes and is under no Change Control Process. No Actions pertain to this document.
Document 8
This document is under the SIMDRACS Board Change Control Process. The following SIMDRACS Actions and Change Controls pertain to this document.
| Name | Date | Ver. | Comments | Link |
|---|
| Action 159 | | | Related to the timing of further information on integration testing | Offsite |
Document 9
| Name | Date | Ver. | Comments | Link |
|---|
| SEMIT Agreed Procedures | 20/11/2006 | 2.0 | AP1 - Registration AP5 - Date Security AP7 - Emergency Comms AP11 - IT System Upgrading AP13 - Data Query | Check offsite here for updates (requires password) |
This document is under the T&SC Change Control Process. The following SIMDRACS Actions and Change Controls pertain to this document.
|
| Name | Date | Ver. | Comments | Link |
|---|
| Action 184 | | | Relates to the Data Query AP number 13, where a manual setting of a Data Query flag is required | Offsite |
| RA412 | 10/01/2007 | | Removes the requirements for setting the Data Query Flag | Onsite |
| RAwww | 25/01/2007 | | Sets out what packets of information are sent when during registration and changing of registration details to the Metered Data Providers in Appendix 3 of Agreed Procedure 1 | Onsite |
Document 10
This document is under the T&SC Change Control Process. No Actions pertain to this document.
Document 11
| Name | Date | Ver. | Comments | Link |
|---|
| Market Trial Plan | 20/11/2006 | 2.0 | This plan was provided by SEMIT and makes some high-level assumptions around the capabilities of the MDPs | Check offsite here for updates (requires password) |
This document is under the control of the SEMIT, and is not under SIMDRACS control. The following SIMDRACS Actions and pertain to this document.
| Name | Date | Ver. | Comments | Link |
|---|
| Action 186 | | | Pertains to whether the trial plan is feasible for Metered Data Providers | Offsite |
Document 12
| Name | Date | Ver. | Comments | Link |
|---|
| Trading Site Clarifications | 01/12/2006 | 0.2 | This documentation was provided to market participants to provide clarity around Trading Sites. This is provided for information only and does not constitute a statement of rules. | Onsite |
This document is under the control of the Regulatory Authorities, and is not under SIMDRACS control. No Actions pertain to this document
Document 13
| Name | Date | Ver. | Comments | Link |
|---|
| Alternative to RA324 | 05/12/2006 | 0.2 | This document describes a possible high-level process to handle the delivery of price-effecting metered demand to the SMO on a Calendar Day basis. | Onsite |
This document is under the control of the Regulatory Authorities, and is not under SIMDRACS control. No Actions pertain to this document
Change Requests
|
| Name | Title | Date | Comments | Link |
|---|
| Rejected Change Control | RA322 | Submitted: 10th August 2006 Resolution: TBC | Interval metering must be installed for anything that can effect price | Onsite
See RA-Legal |
| Postponed Change Control | RA323 | Submitted: 10th August 2006 Resolution: 08 November. Postponed until after SEM go-live | Supplier Units, for the avoidance of doubt, can go negative | Onsite |
| Postponed Change Control | RA324 | Submitted: 10th August 2006 Resolution: 08 November. Postponed until after SEM go-live | Supplier Unit volumes only required for settlement (Week Day) - firm access pricing calculation provided by new site demand data feed from System Operator (Calendar Day) | Onsite |
| Pending Change Control | TSO_RA_CR2 | 13/09/2006 | Requesting EirGrid to impact polling distributed connected generation that is price effecting | Onsite |
| Rejected Change Control | RA333 | Submitted: 19th September 2006 Resolution: TBC | To enshrine AP16 into the Code. Low priority as AP16 has been baselined in SEMIT systems | Onsite
This was rejected due to the publication timelines of the Metered Data. See RAxxx |
| Rejected Change Control | RA334 | Submitted: 19th September 2006 Resolution: TBC | To change the timelines of the Data Query. Medium priority as it impacts the Data Query AP. | Onsite
This was rejected due to |
| Rejected Change Control | RA347 | Submitted: 19th September 2006 Resolution: TBC | Installation of SCADA required for Price Maker or Price Taker | Onsite
This was rejected due to wording difficulties around "Price Taker". See RA |
| Accepted Change Control | SIMDRACS_1b | Submitted: 12th October 2006 Baselined by SIMDRACS Project Co-ordinator on the basis that both groups are working to deliver it | Timing of delivery of W-RMO-ALL-32. This "1b" change request clarifies both SIMDRACS_1 and SIMDRACS_1a which are still available onsite. | Onsite |
| Accepted Change Control | SIMDRACS_2 | Submitted: 5th October 2006 Decision to baseline: 10th October 2006 | Appendix detailing co-operation between SONI and NIE T&D | Onsite |
| Accepted Change Control | SIMDRACS_3 | Submitted: 10th October 2006 Impact returned: 19th October Baselined: 24th October | Changing the "time stamp" field from an optional to a required field | Onsite |
| Accepted Change Control | SIMDRACS_4 | Submitted: 5th October 2006 Impact returned: 19th October Baselined: 24th October | Baselining Appendix 3 of Agreed Procedure 1 scheduled for next SIMDRACS Board Meeting October 10th | Onsite |
| Accepted Change Control | SIMDRACS_5 | Submitted: 16th October 2006 Impact returned: to be agreed on the 19th of October Baselined: 24th October | TIME_CREATED field altered to a per second precision for Version 1.3 of Baselined Document #6 SEM MDP File Format | Onsite |
| Accepted Change Control | SIMDRACS_6 | Submitted: 8th January 2007 Accepted on 23rd January 2007 | Out-of-market trading - historical Supplier Unit volumes need only be 1.5 times maximum contracted generation. Regulatory Requirements document to Version 1.3 | Onsite |
| Accepted Change Control | SIMDRACS_7 | Submitted: 8th January 2007 Accepted on 23rd January 2007 | Out-of-market trading - information to send to suppliers when Supplier Unit volumes set to zero. Regulatory Requirements document to Version 1.3 | Onsite |
| Accepted Change Control | SIMDRACS_8 | 8th January 2007 Accepted on 23rd January 2007 | Allowed values of Actual/Estimated Flag in the file format. SEM-MDP Metered Data File Format set to Version 1.5 | Onsite |
| Accepted Change Control | SIMDRACS_9 | 8th January 2007 Accepted 8th February 2007 | Rules for counting actual reads for "MPRNs" aggregation for out-of-market generation in Ireland | Onsite |
| Accepted Change Control | SIMDRACS_10 | 8th January 2007 Accepted 8th February 2007 | Rules for counting actual reads when two 15-minute readings are aggregated into a half-hourly volume | Onsite |
| Pending Change Control | SIMDRACS_11 | 12th January 2007: (23rd January 2007) Decision to baselined deferred until response to Query 19 with SEMIT | Changes the xml and wsdl of the API interface to remove embedded date from all VALUE fields | Onsite |
| Pending Change Control | SIMDRACS_12 | 25th January 2007: Accepted change control, contingent on acceptance of RAxxx | Set the Data Query Flag permanently to numerical zero | Onsite |
| Pending Change Control | SIMDRACS_13 | 25/01/2007 | To align the Meter Data Format Data Definitions to the changes to the SEM-MDP Metered Data File Format (SIMDRACS_3, SIMDRACS_5, SIMDRACS_8) | Onsite |
| Retired Change Control | RAyyy | 08/01/2007 | Replaces RA333: To bring AP16 into the Code | Onsite
This was amalgamated into RA-Legal |
| Pending Change Control | RAzzz | 08/01/2007 | Replaces RA347: A rewording change | Onsite
This was amalgamated into RA-Legal |
| Pending Change Control | RA412 | 10/01/2007 | Removes the requirements for setting the Data Query Flag | Onsite
(Sent to SEMIT 26th January - formally called RAxxx) |
| Retired Change Control | RAvvv | 25/01/2007 | Metered Data Providers must send in data to the SMO in the event of a failure within 2 Working Days for either technical or communication reasons | Onsite
This was amalgamated into RA-Legal |
| Pending Change Control | |